Construction of the Latterman underpass as part of the Ilirija swimming pool project
Year of construction: 2024
Investor: Municipality of Ljubljana
Location: Tivoli park, Ljubljana
Foto: Eleja IC Aleš Debe
Construction of a railway underpass and a pedestrian walkway from the new Ilirija bathing complex to Tivoli Park. The construction of the underpass was carried out by undercutting, without interrupting traffic under the temporary tunnels, and using continuous excavation. The construction technology influenced the design of the building. In addition to the wall crossing angle, the width of the underpass was also determined by the Latterman’s Alley, which is protected by the ZVKDS. The large span of the underpass has been reduced by two intermediate “V” columns, with a rectangular span measuring 17.11 m and a parallel span 19.52 m.